We are deeply grateful to God for the growth and development of our ministry.
In recent years we have seen an increasing demand for more events and larger camps. In response to this need, there has been an increase in the size of our staff. This has created a need for us to provide more housing for our staff members.
As a result, we are excited to announce the start of a new construction project to build three homes to provide comfort for our dedicated team.
Our plan is to build all 3 houses in parallel, shell construction and installations. Interior work will then be completed one house at a time.
Estimated costs per house: 80.000€
Construction phases | Time period | Description |
---|---|---|
PHASE 1 | March & April 2024 | Prepare the access road and infrastructure, and erect the construction crane. |
PHASE 2 | Fall & Winter 2024 | Obtain building permits. Preparation of foundations and retaining walls. |
PHASE 3 | Spring 2025 | Foundations and slabs. |
PHASE 4 | Summer 2025 | Shell construction of houses including roofs. |
PHASE 5 | Fall & Winter 2025 | Closing of exterior shells including windows and doors, insulation of exterior walls and roofs. Installations. |
PHASE 6 | Spring 2026 | Interior fittings. |
PHASE 7 | Summer 2026 | First house completed and occupied |